MILES ELEMENTARY SCHOOL - REROOFING
APPROVAL OF CHANGE ORDER NO. 1 - $198,381.37 CREDIT
APPROVAL OF CHANGE ORDER NO. 2 - $1,994.00 CREDIT

EXECUTIVE SUMMARY

This project was planned by the architectural firm of Smith & Company Architects. Horus Construction Services is providing construction management services under their continuing services agreement. The scope of work provides for roof replacement.

Change Order No. 1 provides credits for the direct purchase of materials by the District, revision of downspouts, and return of an unused bond. Change Order No. 2 provides a credit for the return of unused contingency funds.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Critical Success Factor 6.a.8 - Provide sufficient student stations to ensure uninterrupted student learning and data gathering as measured by District Operational Goals plan.

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Public Education Capital Outlay (PECO) Maintenance.
Contract Status:
Guaranteed Maximum Price: $592,583.00
Change Order No. 1 Recommended Herein: $198,381.37 Credit
Change Order No. 2 Recommended Herein: $1,994.00 Credit
Revised Guaranteed Maximum Price: $392,207.63

Contract Completion Date: September 2, 2004

EVALUATION

SUBMITTED BY:

J. Thomas Blackwell
General Manager of Construction
(813) 272-4112
James Hamilton
Chief of Staff
(813) 272-4101
6.17
Hillsborough County Public Schools (Florida) * Mtg.#20050712_146 * Section E Item# 6.17