Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, July 26, 2005
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

JUST ELEMENTARY SCHOOL - DEMOLITION & REPLACEMENT
STEWART MIDDLE SCHOOL - CLASSROOM ADDITION, TECHNOLOGY LAB DEMOLITION AND REPLACEMENT
APPROVAL OF CHANGE ORDER NO. 5 (JUST) - $5,286.11 EXTRA
APPROVAL OF CHANGE ORDER NO. 6 (STEWART) - $23,362.11 EXTRA

EXECUTIVE SUMMARY

These projects were planned by The Architectural Practice. On March 12, 2002, the Board appointed the construction management firm of Rodda Construction. A preplanning evaluation determined that the Just Elementary facility could not be renovated in a cost-effective manner. Existing buildings were demolished with the exception of the recently constructed Media Center. A new elementary school to house approximately 576 students was constructed on the site. The existing Stewart Technology Lab was demolished and a replacement lab was constructed to allow the Just multipurpose dining room to be attached to the existing Stewart kitchen which was remodeled to accommodate both schools. A 14 classroom addition to house 308 students at Stewart was constructed. The full-service school components will be relocated on campus to provide better accessibility to the public.

Change Order No. 5 for Just Elementary provides for an adjustment to the Direct Purchase Program. Change Order No. 6 for Stewart Elementary provides for hot water connection to Staff restroom lavatory as required by the Health Department, gas piping for fryers, relocation of kitchen panel in manager's office, and an adjustment to the Direct Purchase Program.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Critical Success Factor 6.a.8 - Provide sufficient student stations to ensure uninterrupted student learning and data gathering as measured by District Operational Goals plan.

FINANCIAL IMPACT (Budgeted: Yes)

These items are included in the District Capital Outlay: Just Elementary is funded by Certificates of Participation Series 2002 and Qualified Zone Academy Bonds 2003. Stewart Elementary is funded by Certificates of Participation Series 2002.
Just Elementary School
Contract Status: (See Attachment)
Revised Guaranteed Maximum Price: $5,342,506.56
Stewart Middle School
Contract Status: (See Attachment)
Revised Guaranteed Maximum Price: $2,247,751.58

EVALUATION

SUBMITTED BY:

J. Thomas Blackwell
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
6.07
Hillsborough County Public Schools (Florida) * Mtg.#20050726_148 * Section E Item# 6.07