This project was planned by the architectural firm of Solah. On March 12, 2002, the Board appointed the construction management firm of Ed Taylor Construction South. The scope of work includes enclosing the courtyard in the exceptional education suite to provide an exercise area and for modification of the bus loading platform and additional restrooms to comply with the Americans with Disabilities Act. It also provides for renovation of the kitchen and installation of new flooring in the cafeteria, correction of site drainage issues, handrail installation, and replacement of cabinets and windows in Buildings 3, 4, 5, 6 and 7 and walkways at the administration building. Change Order No. 5 provides for the final reconciliation of the Direct Purchase Program. Change Order No. 6 provides for the final reconciliation of the Owner Controlled Insurance Program. Change Order No. 7 provides a credit for the return of unused contingency funds. It also provides for exit lights in Building 8 and a door buzzer for the kitchen delivery door.
The architect advises that the referenced project is substantially complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
Critical Success Factor 6.a.8 - Provide sufficient student stations to ensure uninterrupted student learning and data gathering as measured by District Operational Goals plan.
FINANCIAL IMPACT (Budgeted: Yes)
EVALUATION
SUBMITTED BY:
J. Thomas Blackwell
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |