Approve Change Order No. 3 in the Credit Amount of $71,478.18 and Acceptance of Project for Classrooms for Kids Addition at
Burnett Middle School

EXECUTIVE SUMMARY

On November 9, 2006, the Board appointed Holmes Hepner and Associates Architects and J.O. DeLotto & Sons, Inc. to provide design and construction management services. The scope of work provided for an additional 10 classrooms. This addition was necessary to meet class size reduction requirements.

This change order provides a credit for project savings and the return of unused contingency funds.

The architect advises that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

* Construct and maintain facilities that create an environment conducive to teaching and learning

FINANCIAL IMPACT (Budgeted: Yes)

This item was included in the District Capital Outlay: Classrooms for Kids.

Contract Status:
Guaranteed Maximum Price: $1,839,477.00
Change Orders Previously Approved: $339,096.39 Credit
Change Order Recommended Herein: $71,478.18 Credit
Revised Guaranteed Maximum Price: $1,428,902.43
Payments to Date: $1,316,887.90
Balance Due: $112,014.53
Revised Construction Cost: $1,748,012.40

Contract Completion Date: August 4, 2008
Substantial Completion Date: August 4, 2008

EVALUATION

SUBMITTED BY: Alice Sutton, Project Coordinator

Rory Salimbene
General Manager of Construction
(813) 272-4112
Daniel J. Valdez
Deputy Superintendent
(813) 272-4166
A 6.10
Hillsborough County Public Schools (Florida) * Mtg.#20100420_398 * Section A Item# 6.10