Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, April 20, 2010
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

Approve Change Order No. 4 in the Credit Amount of $224,565.24 and Acceptance of Project for Classrooms for Kids Addition at
Sessums Elementary School

EXECUTIVE SUMMARY

On May 20, 2008, the Board appointed the architectural firm of Woodroffe Corporation Architects to provide design services. On July 15, 2008, the Board appointed the construction management firm of Batson-Cook Company. The scope of work provided for an additional 16 classrooms. This addition was necessary to meet class size reduction requirements.

This change order provides a credit for project savings and the return of unused contingency funds.

The architect advises that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

* Construct and maintain facilities that create an environment conducive to teaching and learning

FINANCIAL IMPACT (Budgeted: Yes)

This item was included in the District Capital Outlay: Classrooms for Kids.

Contract Status:
Guaranteed Maximum Price: $2,461,571.00
Change Orders Previously Approved: $632,228.74 Credit
Change Order Recommended Herein: $224,565.24 Credit
Revised Guaranteed Maximum Price: $1,604,777.02
Payments to Date: $1,581,840.11
Balance Due: $22,936.91
Revised Construction Cost: $2,192,431.55

Contract Completion Date: July 29, 2009
Substantial Completion Date: July 29, 2009

EVALUATION

SUBMITTED BY: Eugene Runnels, Project Coordinator

Rory Salimbene
General Manager of Construction
(813) 272-4112
Daniel J. Valdez
Deputy Superintendent
(813) 272-4166
A 6.13
Hillsborough County Public Schools (Florida) * Mtg.#20100420_398 * Section A Item# 6.13