On February 13, 2007, the Board appointed Rodriguez + Architecture / AIA / PA and Christiano Construction Company, Inc. to provide design and construction management services. The renovation of existing facilities included replacement or refurbishment of interior finishes and hardware; power, lighting, and low-voltage system upgrades; mechanical and drainage system repairs, and exterior repairs; waterproofing and painting. The administration building was remodeled and reconfigured.
The architect advises that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
FINANCIAL IMPACT (Budgeted: Yes)
This item was included in the District Capital Outlay: Public Education Capital Outlay (PECO) Construction 06-07.
Contract Status:
Guaranteed Maximum Price: $3,070,000.00
Approved Change Orders: $385,687.29 Credit (See Attachment)
Revised Guaranteed Maximum Price: $2,684,312.71
Payments to Date: $2,649,575.10
Balance: $34,737.61
Revised Construction Cost: $3,190,919.75
Original Completion Date: April 8, 2009
Approved Time Extension: 25 Calendar Days (See Attachment)
Revised Completion Date: May 3, 2009
Substantial Completion Date: April 30, 2009
EVALUATION
SUBMITTED BY: John Williams, Project Coordinator
Rory Salimbene
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
A 6.13d | |
Hillsborough County Public Schools (Florida) * Mtg.#20100615_402 * Section A Item# 6.13d |