Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, July 27, 2010
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

Approve Acceptance of Project for Fire Alarm and Intercom Systems Replacement at
Colson Elementary School

EXECUTIVE SUMMARY

Anston-Greenlees, Inc. was selected from the approved Continuing Services Consultants list to provide design services. On May 5, 2009, the Board awarded the contract for construction to the low bidder, Inter-Bay Electric Co., Inc. The scope of work provided for replacement of the fire alarm and intercom systems.

The engineer advises that the referenced project is substantially complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

* Construct and maintain facilities that create an environment conducive to teaching and learning

FINANCIAL IMPACT (Budgeted: Yes)

This item was included in the District Capital Outlay: Public Education Capital Outlay (PECO) Maintenance.

Contract Status:
Contract Sum: $138,269.00
Approved Change Order: $4,400.00 Credit (See Attachment)
Revised Contract Sum: $133,869.00
Payments to Date: $120,482.10
Balance Due: $13,386.90
Revised Construction Cost: $133,869.00

Contract Completion Date: July 31, 2009
Substantial Completion Date: July 30, 2009

EVALUATION

SUBMITTED BY: Bob Harwell, Electrical Engineer

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
A 6.04b
Hillsborough County Public Schools (Florida) * Mtg.#20100727_416 * Section A Item# 6.04b