Facilities Action Item |
DATE: Tuesday, July 20, 2010
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
On April 21, 2008, the Board approved an interlocal agreement with Hillsborough County for the expansion of the existing library at Sulphur Springs Elementary School. The agreement specified the County and the District would jointly design, operate, and maintain the facility, with construction accomplished by the District. At completion, the District owned the 3,300 to 3,500 square foot expanded facility, with a joint right of use between both parties.
District staff selected The Architectural Practice, Inc. and W.G. Mills, Inc. from the approved Continuing Services Consultants list to provide design and construction management services.
The architect advises that the referenced project is substantially complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
FINANCIAL IMPACT (Budgeted: Yes)
The County agreed to reimburse the District up to $770,000 for the project. Therefore, there was no financial impact to the District.
Contract Status:
Guaranteed Maximum Price: $699,446.00
Approved Change Orders: $126,649.10 Credit (See Attachment)
Revised Guaranteed Maximum Price: $572,796.90
Payments to Date: $548,951.35
Balance Due: $23,845.55
Revised Construction Cost: $642,499.92
Contract Completion Date: January 15, 2010
Substantial Completion Date: January 27, 2010
EVALUATION
SUBMITTED BY: Jill Edwards, Project Coordinator
Rory Salimbene
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
A 6.11h | |
Hillsborough County Public Schools (Florida) * Mtg.#20100720_415 * Section A Item# 6.11h |