Facilities Action Item |
DATE: Tuesday, July 20, 2010
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
Anston-Greenlees, Inc. was selected from the approved Continuing Services Consultants list to provide design services. On May 20, 2008, the Board awarded the contract for construction to the low bidder, Air Mechanical & Service Corp. The scope of work provided for modification of the HVAC systems at Adams, Eisenhower, and Memorial Middle Schools and B.T. Washington Elementary School.
The engineer advises that the referenced project is substantially complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
FINANCIAL IMPACT (Budgeted: Yes)
EVALUATION
SUBMITTED BY: Ernie MacFerran, Project Coordinator
Rory Salimbene
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
A 6.11a | |
Hillsborough County Public Schools (Florida) * Mtg.#20100720_415 * Section A Item# 6.11a |