Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, August 10, 2010
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

Approve Acceptance of Project for Heating, Ventilating, and Air Conditioning (HVAC) Renovation at
Roland Park K-8 School

EXECUTIVE SUMMARY

Lyle Engineering Group, Inc. was selected from the approved Continuing Services Consultants list to provide design services. On May 19, 2009, the Board awarded the contract for construction to the low bidder, Air Mechanical & Service Corp. The scope of work provided for replacement of the existing ice harvester cooling plant with a new plant incorporating an air cooled chiller and ice storage tanks.

The engineer advises that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

* Construct and maintain facilities that create an environment conducive to teaching and learning

FINANCIAL IMPACT (Budgeted: Yes)

This item was included in the District Capital Outlay: Local Millage.

Contract Status:
Contract Sum: $641,400.00
Approved Change Orders: $10,988.81 Credit (See Attachment)
Revised Contract Sum: $630,411.19
Payments to Date: $572,802.31
Balance Due: $57,608.88
Revised Construction Cost: $630,411.19

Required Substantial Completion Date: August 7, 2009
Substantial Completion Date: August 7, 2009

EVALUATION

SUBMITTED BY: Alice Sutton, Project Coordinator

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
A 6.06b.
Hillsborough County Public Schools (Florida) * Mtg.#20100810_417 * Section A Item# 6.06b.