EXECUTIVE SUMMARY

This project was planned by the architectural firm of Alfonso Architects, Inc. On March 12, 2002, the Board appointed the construction management firm of J.O. DeLotto & Sons, Inc. The scope of work included construction of a new K-8 school to house 1,226 students.

The architect advises that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

* Construct and maintain facilities that create an environment conducive to teaching and learning

FINANCIAL IMPACT (Budgeted: Yes)

This item was included in the District Capital Outlay: Certificates of Participation Series 2003.

Contract Status:
Guaranteed Maximum Price: $11,277,514.00
Approved Change Orders: $1,634,417.74 Credit (See Attachment)
Revised Guaranteed Maximum Price: $9,643,096.26
Payments to Date: $9,574,045.56
Balance Due: $69,050.70
Revised Construction Cost: $12,189,489.04

Required Substantial Completion Date: May 6, 2005
Approved Time Extension: 21 Calendar Days (See Attachment)
Revised Required Substantial Completion Date: May 27, 2005
Substantial Completion Date: June 16, 2005

EVALUATION

SUBMITTED BY: Alice Sutton, Project Coordinator

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
A 6.05i
Hillsborough County Public Schools (Florida) * Mtg.#20101026_429 * Section A Item# 6.05i