Facilities Action Item |
DATE: Tuesday, October 26, 2010
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
These projects provide for renovation of Caminiti Exceptional Center and Chiaramonte Elementary School and renovation of the heating, ventilating, and air conditioning (HVAC) system at Hill Middle School. Appointment of qualified construction management firms for the referenced projects is required.
Florida Statutes and School Board policy outline the process and requirements for selection of architects, engineers, and construction managers. Attachment A summarizes the process. The process provides for the identification of the most highly qualified firms by a Professional Services Selection Committee that includes representatives from several District divisions and the community. Attachment C identifies the specific committee members participating in this selection and the organization represented by each.
A total of twenty-three firms responded to the solicitation for construction management of the renovations at Caminiti Exceptional Center, Chiaramonte Elementary School, and Hill Middle School. The solicitation is included on Attachment B. Attachments D and E record the results of the Committee's evaluation of these firms at each phase of the process.
Staff has successfully concluded negotiations with the firms deemed most highly qualified by the Selection Committee to provide the required services. Based on the Selection Committee ranking and successful negotiations, staff recommends appointment of the firms and award of the corresponding fees as indicated.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
FINANCIAL IMPACT (Budgeted: Yes)
Construction budgets are as follows: $3,683,811 for Caminiti, $2,458,600 for Chiaramonte, and $3,495,701 for Hill. Funding will derived from District Capital Outlay: Local Millage for Caminiti, Capital Outlay and Debt Service (CO & DS) 2010 for Chiaramonte, and Public Education Capital Outlay (PECO) Maintenance for Hill.
EVALUATION
SUBMITTED BY: Rory Salimbene, General Manager of Construction
Rory Salimbene
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
A 6.02 | |
Hillsborough County Public Schools (Florida) * Mtg.#20101026_429 * Section A Item# 6.02 |