Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, October 2, 2007
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

Approve Construction Documents and Guaranteed Maximum Price for
Middle School "RR" (Northwest), New Facility

EXECUTIVE SUMMARY

This project is being planned by the architectural firm of Wilder Architecture, Inc. On June 7, 2005, the Board appointed the construction management firm of Allstate Construction, Inc. As of the current boundaries, relief will be provided for Davidsen, Farnell, and Martinez Middle Schools.

Approval of the guaranteed price will provide a maximum cost for the facility. Project completion is scheduled for July 21, 2008.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Provide adequate school facilities for the accomplishment of all District Goals and Critical Success Factors.

FINANCIAL IMPACT (Budgeted: Yes)

Construction cost is warranted at $20,407,140, which includes $31,801 for extraordinary conditions (temporary busloop and removal of underground infrastructure from portable classrooms). The construction budget is $20,407,140. This item is included in the District Capital Outlay: Certificates of Participation Series 2006.

EVALUATION

SUBMITTED BY: Jill Edwards, Project Coordinator

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
A 6.05b
Hillsborough County Public Schools (Florida) * Mtg.#20071002_267 * Section A Item# 6.05b