Facilities Action Item |
DATE: Tuesday, October 16, 2007
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
On January 17, 2006, the Board appointed The Architectural Practice, Inc. and Ellis Construction Company, Inc. to provide design and construction management services for this new facility, which reuses the Collins Elementary School design. As of the current boundaries, this school relieves Bryant Elementary School. On February 13, 2007, the Board approved the guaranteed maximum price for the project.
This change order provides a credit for the direct purchase of materials by the District, in accordance with the Direct Purchase Program.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
FINANCIAL IMPACT (Budgeted: Yes)
This item is included in the District Capital Outlay: Certificates of Participation Series 2004C ($10,333,649) and Classrooms for Kids 2003-04 ($2,669,722).
Contract Status:
Guaranteed Maximum Price: $13,003,371.00
Change Orders Previously Approved: $3,803,695.06 Credit
Change Order Recommended Herein: $122,868.21 Credit
Revised Guaranteed Maximum Price: $9,076,807.73
Revised Construction Cost: $12,778,921.89
Contract Completion Date: July 31, 2007
EVALUATION
SUBMITTED BY: Alice Sutton, Project Coordinator
Rory Salimbene
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
A 6.06 | |
Hillsborough County Public Schools (Florida) * Mtg.#20071016_268 * Section A Item# 6.06 |