Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, October 16, 2007
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

Approve Change Order No. 4 in the Credit Amount of $27,004.70 for Site Work at
Deer Park Elementary School

EXECUTIVE SUMMARY

On January 17, 2006, the Board appointed The Architectural Practice, Inc. and Ellis Construction Company, Inc. to provide design and construction management services for Deer Park Elementary School. This new facility reuses the Collins Elementary School design. As of the current boundaries, this school relieves Bryant Elementary School.

On February 13, 2007, the Board approved the guaranteed maximum price for site work associated with the new school. The site work project includes onsite and offsite utilities, paving, and earthwork required for the construction of the school.

This change order provides a credit for the direct purchase of materials by the District, in accordance with the Direct Purchase Program.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Provide adequate school facilities for the accomplishment of all District Goals and Critical Success Factors.

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: 2 Mill.

Contract Status:
Guaranteed Maximum Price: $3,295,132.00
Change Orders Previously Approved: $258,266.03 Credit
Change Order Recommended Herein: $27,004.70 Credit
Revised Guaranteed Maximum Price: $3,009,861.27
Revised Construction Cost: $3,301,808.19

Contract Completion Date: July 31, 2007

EVALUATION

SUBMITTED BY: Alice Sutton, Project Coordinator

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
A 6.05
Hillsborough County Public Schools (Florida) * Mtg.#20071016_268 * Section A Item# 6.05