Facilities Action Item |
DATE: Tuesday, October 16, 2007
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
On January 17, 2006, the Board appointed The Architectural Practice, Inc. and Ellis Construction Company, Inc. to provide design and construction management services for Deer Park Elementary School. This new facility reuses the Collins Elementary School design. As of the current boundaries, this school relieves Bryant Elementary School.
On February 13, 2007, the Board approved the guaranteed maximum price for site work associated with the new school. The site work project includes onsite and offsite utilities, paving, and earthwork required for the construction of the school.
This change order provides a credit for the direct purchase of materials by the District, in accordance with the Direct Purchase Program.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
FINANCIAL IMPACT (Budgeted: Yes)
EVALUATION
SUBMITTED BY: Alice Sutton, Project Coordinator
Rory Salimbene
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
A 6.05 | |
Hillsborough County Public Schools (Florida) * Mtg.#20071016_268 * Section A Item# 6.05 |