Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, September 18, 2007
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

Approve Schematic Design and Design Development Phases for Renovation at
Limona Elementary School
Added Attachment - Page 8 (Estimate 2 of 4)

EXECUTIVE SUMMARY

On February 13, 2007, the Board appointed rojo Architecture and Ellis Construction Company, Inc. to provide design and construction management services. The renovation of existing facilities includes painting throughout the campus, replacement of vinyl composition tile (VCT) flooring and base, fire rating upgrades at classroom walls, miscellaneous architectural, plumbing, and electrical improvements, upgrades to the fire alarm, security, intercom, and data systems to meet code and current standards, and repair of deteriorated structural elements at columns and footings around the perimeter of the circular classroom building, Media Center, and Building 7.

Approval of the schematic design and design development phases will allow the architect to proceed with construction documents. Project completion is scheduled for February 2009.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Provide adequate school facilities for the accomplishment of all District Goals and Critical Success Factors.

FINANCIAL IMPACT (Budgeted: Yes)

The project is currently funded at $3,440,000. The estimate of probable cost is $3,264,610. This item is included in the District Capital Outlay: Public Education Capital Outlay (PECO) Construction 06-07.

EVALUATION

SUBMITTED BY: Eugene Runnels, Project Coordinator



Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
A 6.07R
Hillsborough County Public Schools (Florida) * Mtg.#20070918_266 * Section A Item# 6.07R