Facilities Action Item |
DATE: Tuesday, November 20, 2007
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
This project was planned by the architectural firm of Carruthers and Associates Architects P.A. On January 16, 2007, the Board appointed the construction management firm of Manhattan Construction Company. The renovation of existing facilities provides for replacement of intercom, fire alarm, and heating, ventilating, and air conditioning (HVAC) systems, new roofing, miscellaneous new finishes, Americans with Disabilities Act (ADA) upgrades, and new kitchen freezer and hood.
This change order provides for correction of miscellaneous code deficiencies in the 7 existing pods located in Buildings 2, 3, and 5. A time extension is included for completion of the work.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
FINANCIAL IMPACT (Budgeted: Yes)
This item is included in the District Capital Outlay: Community Investment Tax ($2,942,709.34) and Student Nutrition Services ($43,000.00).
Contract Status:
Guaranteed Maximum Price: $3,343,000.00
Change Orders Previously Approved: $357,290.66 Credit
Change Order Recommended Herein: $74,236.19 Extra
Revised Guaranteed Maximum Price: $3,059,945.53
Revised Construction Cost: $3,526,123.37
Original Completion Date: December 11, 2007
Time Extension Recommended Herein: 20 Calendar Days
Revised Completion Date: December 31, 2007
EVALUATION
SUBMITTED BY: Eugene Runnels, Project Coordinator
Rory Salimbene
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
A 6.25 | |
Hillsborough County Public Schools (Florida) * Mtg.#20071120_270 * Section A Item# 6.25 |