EXECUTIVE SUMMARY
This project was planned by the architectural firm of Abell Garcia Architects, P.A. On January 13, 2004, the Board appointed the construction management firm of R.J. Bunbury Company, Inc. for renovation of the school. On December 14, 2004, the Board approved an increase in the project’s scope for replacement of the existing food service facility with a new Multi-Purpose Building, and a Classroom for Kids Addition providing 12 primary classrooms. The Board previously approved separate Guaranteed Maximum Prices (GMP's) for the Classroom for Kids Addition and the Multi-Purpose Building.
This change order to the Multi-Purpose Building project provides for connection of roof drains to the stormwater system, a new flammable storage enclosure, the addition of a corrugated metal soffit to walkway canopies to conceal exposed conduit and fasteners, revisions to ceiling and lighting designs for the kitchen, and site modifications required by the City of Tampa and received after the GMP was approved.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
FINANCIAL IMPACT (Budgeted: Yes)
This item is included in the District Capital Outlay: Capital Outlay and Debt Service ($1,632,654.00) and Public Education Capital Outlay (PECO) Construction ($506,046.90).
Contract Status:
Guaranteed Maximum Price: $2,069,136.00
Change Orders Previously Approved: $69,564.90 Extra
Change Order Recommended Herein: $73,900.68 Extra
Revised Guaranteed Maximum Price: $2,212,601.58
Revised Construction Cost: $2,212,601.58
Contract Completion Date: May 25, 2007
EVALUATION
SUBMITTED BY: John Williams, Project Coordinator
Rory Salimbene
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
A 6.19 | |
Hillsborough County Public Schools (Florida) * Mtg.#20071120_270 * Section A Item# 6.19 |