Facilities Action Item |
DATE: Tuesday, December 11, 2007
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
On February 13, 2007, the Board appointed John J. McKenna Architect P.A. and The Morganti Group, Inc. to provide design and construction management services. Planned interior work includes accessibility improvements to comply with Americans with Disabilities Act (ADA) requirements; upgrades to lighting, the fire alarm system, and signage to meet current standards; general painting and ceiling replacement throughout the campus; the addition of fire sprinklers for Building 1; and replacement of marker boards and cabinets where needed. Exterior work includes roof repairs, and ingress and egress improvements. Project completion is scheduled for December 2008.
Approval of the design development documents will allow the architect to proceed with construction documents.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
FINANCIAL IMPACT (Budgeted: Yes)
The project is currently funded at $4,380,000. The estimate of probable cost is $4,350,000. This item is included in the District Capital Outlay: Public Education Capital Outlay (PECO) Construction 06-07.
EVALUATION
SUBMITTED BY: Ellis Curry, Project Coordinator
Rory Salimbene
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
A 6.04A | |
Hillsborough County Public Schools (Florida) * Mtg.#20071211_271 * Section A Item# 6.04A |