Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, December 11, 2007
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

Approve Design Development Documents for
High School "UUU" (Plant City), New Facility

EXECUTIVE SUMMARY

On December 12, 2006, the Board appointed Long & Associates Architects/Engineers, Inc. and HCBeck, Ltd. to provide design and construction management services. As of the current boundaries, this school relieves Armwood, Durant, and Plant City High Schools. Project completion is scheduled prior to the 2009-10 school year.

Approval of the design development documents will allow the architect to proceed with construction documents.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Provide adequate school facilities for the accomplishment of all District Goals and Critical Success Factors.

FINANCIAL IMPACT (Budgeted: Yes)

The project is currently funded at $48,980,520. The estimate of probable cost is $48,923,520. This item is included in the District Capital Outlay: Certificates of Participation Series 2007.

EVALUATION

SUBMITTED BY: John Williams, Project Coordinator

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
A 6.04B
Hillsborough County Public Schools (Florida) * Mtg.#20071211_271 * Section A Item# 6.04B