Approve Change Order No. 5 in the
Amount of $117,077.18 Extra for
Hammond Elementary School, New Facility
EXECUTIVE SUMMARY
On November 22, 2005, the Board appointed Holmes Hepner and Associates Architects and Greater Bay Construction Co., Inc. to provide design and construction management services. This facility is a modification of the Pizzo Elementary School design. The school opened in August 2007 and relieved overcrowding at Citrus Park, McKitrick, and Schwarzkopf Elementary Schools.
This change order provides for revisions to the parking lot and emergency rescue windows in Buildings 2, 3, and 4 to meet code requirements; relocation of reclaimed waterline northwest of Building 1 to address an unforeseen condition; and the addition of miscellaneous owner-requested items.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
FINANCIAL IMPACT (Budgeted: Yes)
This item is included in the District Capital Outlay: Certificates of Participation Series 2002.
Contract Status:
Guaranteed Maximum Price: $11,927,498.00
Change Orders Previously Approved: $3,275,187.51 Credit
Change Order Recommended Herein: $117,077.18 Extra
Revised Guaranteed Maximum Price: $8,769,387.67
Revised Construction Cost: $12,011,473.50
Contract Completion Date: June 25, 2007
EVALUATION
SUBMITTED BY: Ellis Curry, Project Coordinator
Rory Salimbene
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |