Facilities Action Item |
DATE: Tuesday, January 15, 2008
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
Approve Change Order No. 8 in the Amount of $72,779.56 Net Extra and a Time Extension of 78 Calendar Days for the Gymnasium Remodel and ROTC Renovation at
Hillsborough High School
EXECUTIVE SUMMARY
This project was planned by the architectural firm of Wilder Architecture, Inc. On July 11, 2006, the Board awarded the contract to the low bidder, Greater Bay Construction Co., Inc. The scope of work provides for remodeling of the existing Gymnasium and renovation of a single story wing used for ROTC and classrooms.
This change order provides for additional scope of work (storage building demolition, additional door replacements, exhaust fan replacements, science lab renovation, plumbing corrections, lead paint abatement, brick wall restoration, GFCI receptacles, and wood floor base in lieu of vinyl) and unforeseen conditions (requirement for additional framing and floor joist replacement). A time extension is included for completion of the work. Also included is a credit for deletion of volleyball sleeves from the project. The existing sleeves will be reused.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
FINANCIAL IMPACT (Budgeted: Yes)
EVALUATION
SUBMITTED BY: Eugene Runnels, Project Coordinator
Rory Salimbene
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
A 6.14 | |
Hillsborough County Public Schools (Florida) * Mtg.#20080115_285 * Section A Item# 6.14 |