John J. McKenna Architect P.A. and J.B.D. Construction, Inc. were selected from the approved Continuing Services Consultants list to provide design and construction management services. The scope of work provides for interior/exterior painting at Colson Elementary School and interior painting at Lopez Elementary School.
Change Order No. 2 provides a credit for the return of unused contingency funds. Change Order No. 3 provides for final reconciliation of the Direct Purchase Program.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
Provide adequate school facilities for the accomplishment of all District Goals and Critical Success Factors.
FINANCIAL IMPACT (Budgeted: Yes)
This item is included in the District Capital Outlay: Public Education Capital Outlay (PECO) Maintenance.
Contract Status:
Guaranteed Maximum Price: $280,000.00
Change Order Previously Approved: $13,867.00 Extra
Change Order No. 2 Recommended Herein: $2,000.00 Credit
Change Order No. 3 Recommended Herein: $13,516.44 Credit
Revised Guaranteed Maximum Price: $278,350.56
Revised Construction Cost: $291,054.75
Contract Completion Date: August 10, 2007
EVALUATION
SUBMITTED BY: Jill Edwards, Project Coordinator
Rory Salimbene
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
A 6.13 | |
Hillsborough County Public Schools (Florida) * Mtg.#20080115_285 * Section A Item# 6.13 |