Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, March 4, 2008
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

Approve Acceptance of Project for Chiller Plant Modification at
Maniscalco Elementary School

EXECUTIVE SUMMARY

This project was planned by the engineering firm of Hahn Engineering, Inc. On March 14, 2006, the Board awarded the contract to the low bidder, Air Mechanical & Service Corp. The scope of work provided for the replacement of mechanical system components, including the chillers and air handlers.

The engineer advises that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Provide adequate school facilities for the accomplishment of all District Goals and Critical Success Factors.

FINANCIAL IMPACT (Budgeted: Yes)

This item was included in the District Capital Outlay: 2 Mill.

Contract Status:
Contract Sum: $912,472.00
Change Orders Previously Approved: $116,403.03 Credit
Revised Contract Sum: $796,068.97
Payments to Date: $717,725.70
Balance Due: $78,343.27
Revised Construction Cost: $969,615.97

Original Completion Date: August 19, 2006
Time Extensions Previously Approved: 312 Calendar Days
Revised Completion Date: June 27, 2007
Substantial Completion Date: June 27, 2007

EVALUATION

SUBMITTED BY: Ernie MacFerran, Mechanical Engineer

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
A 6.30
Hillsborough County Public Schools (Florida) * Mtg.#20080304_289 * Section A Item# 6.30