EXECUTIVE SUMMARY
The Walter Fedy Group, Inc. and J.B.D. Construction, Inc. were selected from the approved Continuing Services Consultants list to provide design and construction management services. The scope of work included replacement of parking areas relinquished due to roadway widening, improved ingress and egress, and reconfiguration of parent pick-up/drop-off and faculty parking areas. This work was necessitated by Hillsborough County's planned improvements to Boyette Road and Balm Riverview Road.
The engineer advises that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
Provide adequate school facilities for the accomplishment of all District Goals and Critical Success Factors.
FINANCIAL IMPACT (Budgeted: Yes)
EVALUATION
SUBMITTED BY: James Lipsey, Project Coordinator
Rory Salimbene
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
A 6.47 | |
Hillsborough County Public Schools (Florida) * Mtg.#20080415_291 * Section A Item# 6.47 |