Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, May 6, 2008
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

Approve Change Order No. 3 in the Amount of $18,777.20 Extra for Roofing and HVAC Replacement at
Chamberlain High School

EXECUTIVE SUMMARY

Tagliarini Architectural Group, PA was selected from the approved Continuing Services Consultants list to provide architectural services. On May 29, 2007, the Board awarded the contract to the low bidder, Cason Construction Management, Inc. The scope of work includes a new roof over the Gym and Cafeteria and replacement of the heating, ventilating, and air conditioning (HVAC) system.

This change order provides for District-requested HVAC control improvements, and duct modifications necessitated by unforeseen existing conditions.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Provide adequate school facilities for the accomplishment of all District Goals and Critical Success Factors.

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Public Education Capital Outlay (PECO) Maintenance ($809,792) and 2 Mill ($320,000).

Contract Status:
Contract Sum: $1,129,792.00
Change Orders Previously Approved: $107,203.01 Credit
Change Order Recommended Herein: $18,777.20 Extra
Revised Contract Sum: $1,041,366.19
Revised Construction Cost: $1,160,647.19

Contract Completion Date: August 17, 2007

EVALUATION

SUBMITTED BY: Ernie MacFerran, Mechanical Engineer

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
A 6.16
Hillsborough County Public Schools (Florida) * Mtg.#20080506_292 * Section A Item# 6.16