EXECUTIVE SUMMARY

Wilder Architecture, Inc. was selected from the approved Continuing Services Consultants list to provide design services. On July 11, 2006, the Board awarded the contract to the low bidder, Greater Bay Construction Co., Inc. The scope of work provided for remodeling of the existing Gymnasium and renovation of a single story wing used for ROTC and classrooms.

The architect advises that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Provide adequate school facilities for the accomplishment of all District Goals and Critical Success Factors.

FINANCIAL IMPACT (Budgeted: Yes)

This item was included in the District Capital Outlay: Community Investment Tax 2006.

Contract Status:
Contract Sum: $4,018,300.00
Change Orders Previously Approved: $102,911.80 Credit
Revised Contract Sum: $3,915,388.20
Payments to Date: $3,748,719.03
Balance Due: $166,669.17
Revised Construction Cost: $4,497,989.11

Original Completion Date: April 16, 2007
Time Extensions Previously Approved: 185 Calendar Days
Revised Completion Date: October 18, 2007
Substantial Completion Date: October 18, 2007

EVALUATION

SUBMITTED BY: Eugene Runnels, Project Coordinator

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
A 6.17c