Approve Change Order No. 4 in the Credit Amount of $188,181.12 for
Reddick Elementary School, New Facility

EXECUTIVE SUMMARY

This project was planned by the architectural firm of Harvard Jolly, Inc. On July 11, 2006, the Board appointed the construction management firm of HCBeck, Ltd. This new facility will relieve overcrowding at Cypress Creek Elementary School.

This change order provides a credit for the direct purchase of materials by the District, in accordance with the Direct Purchase Program.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Provide adequate school facilities for the accomplishment of all District Goals and Critical Success Factors.

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Certificates of Participation Series (CoPS) 06 ($7,843,871) and High Growth District Capital Outlay Assistance Grant ($6,306,175).

Contract Status:
Guaranteed Maximum Price: $14,150,046.00
Change Orders Previously Approved: $3,574,713.55 Credit
Change Order Recommended Herein: $188,181.12 Credit
Revised Guaranteed Maximum Price: $10,387,151.33
Revised Construction Cost: $13,934,787.83

Contract Completion Date: July 31, 2008

EVALUATION

SUBMITTED BY: Alice Sutton, Project Coordinator

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
A 6.09