Approve Change Order No. 3 in the Credit Amount of $588,398.25 and Change Order No. 4 in the Amount of $59,085.20 Extra for Renovation at
Wimauma Elementary School

EXECUTIVE SUMMARY

This project was planned by the architectural firm of Fleischman Garcia Architects. On January 16, 2007, the Board appointed the construction management firm of Allstate Construction, Inc. The renovation of existing facilities provides for required walkway lighting; signage, restroom, plumbing fixture, and door hardware upgrades for compliance with the Americans with Disabilities Act (ADA); heating, ventilating, and air conditioning (HVAC) system replacement at selected buildings; exhaust fan replacements throughout the school; interior painting; electrical equipment and distribution system replacements; lighting upgrades; new exterior doors; new fire alarm and telephone systems; replacement of most site fencing; and reroofing and brick repointing on selected buildings. Additionally, the Administrative Suite will be reconfigured for improved operations, and Student Dining expanded to include a multipurpose room with stage and a Faculty Dining space.

Change Order No. 3 provides a credit for the direct purchase of materials by the District, in accordance with the Direct Purchase Program. Change Order No. 4 provides for miscellaneous unforeseen requirements including missing through wall duct at existing air conditioning units; modifications to the existing subflooring for the new concrete slab; rerouting of underground conduit interfering with a new classroom addition; and remediation of selected ductwork and markerboards.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Provide adequate school facilities for the accomplishment of all District Goals and Critical Success Factors.

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Qualified Zone Academy Bonds ($2,418,631) and Public Education Capital Outlay 2005-2006 ($2,012,606).

Contract Status:
Guaranteed Maximum Price: $4,431,237.00
Change Orders Previously Approved: $33,898.72 Extra
Change Order No. 3 Recommended Herein: $588,398.25 Credit
Change Order No. 4 Recommended Herein: $59,085.20 Extra
Revised Guaranteed Maximum Price: $3,935,822.67
Revised Construction Cost: $4,490,203.43

Contract Completion Date: August 30, 2008

EVALUATION

SUBMITTED BY: Ellis Curry, Project Coordinator

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
A 6.19
Hillsborough County Public Schools (Florida) * Mtg.#20080715_295 * Section A Item# 6.19