Facilities Action Item |
DATE: Tuesday, July 15, 2008
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
On September 7, 2004, the Board approved the appointment of The Rosier Alliance and J.B.D. Construction, Inc. to provide design and construction management services for renovations at DeSoto Elementary School. On March 14, 2006, the Board approved the reassignment of the contract for design services to RHC, Inc. due to the withdrawal of The Rosier Alliance from the project. (Prior to assuming the role of lead designer, RHC, Inc. was an engineering consultant to The Rosier Alliance on this project.) The scope of work provides for the renovation of gang toilets for Americans with Disabilities Act (ADA) accessibility, upgrading of fire alarm and security systems, restoration of wood floors in old classrooms, telephone system replacement, and door hardware replacement for ADA accessibility. Mechanical work includes replacement of four classroom air conditioning units, main electrical switch gear, and electrical panels. Exterior work includes painting, dumpster enclosure relocation, correction of site grading issues, and the addition of perimeter security fencing and gates, bus drop-off canopy, and ramps to provide ADA accessibility.
This change order provides for re-roofing of Buildings 1 and 2, and includes costs for interim repairs prior to the re-roofing. A time extension of 21 calendar days is included for completion of the work.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
FINANCIAL IMPACT (Budgeted: Yes)
EVALUATION
SUBMITTED BY: Alice Sutton, Project Coordinator
Rory Salimbene
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
A 6.18 | |
Hillsborough County Public Schools (Florida) * Mtg.#20080715_295 * Section A Item# 6.18 |