Facilities Action Item |
DATE: Tuesday, July 29, 2008
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
On November 9, 2006, the Board appointed John J. McKenna Architect P.A. and W.G. Mills, Inc. to provide design and construction management services. The architectural agreement for the classrooms additions at Maniscalco and Northwest Elementary Schools and Marshall and Martinez Middle Schools and the construction management agreement for the classroom additions at Hunter's Green, Maniscalco, and Walden Lake Elementary Schools and Marshall Middle School are being amended to add interior and exterior painting at Marshall Middle School. The scope of work includes interior painting throughout the facility and painting of exterior trim and canopies. Project completion is scheduled for August 8, 2008.
Approval of the guaranteed maximum price will establish the cost for the painting maintenance project.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
FINANCIAL IMPACT (Budgeted: Yes)
Construction cost is warranted at $349,839. The construction budget is $350,000. This item is included in the District Capital Outlay: Public Education Capital Outlay (PECO) Maintenance.
EVALUATION
SUBMITTED BY: Eugene Runnels, Project Coordinator
Rory Salimbene
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
A 6.03 | |
Hillsborough County Public Schools (Florida) * Mtg.#20080729_296 * Section A Item# 6.03 |