Facilities Action Item |
DATE: Tuesday, August 19, 2008
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
On December 18, 2007, the Board appointed The Architectural Practice, Inc. and Batson-Cook Company to provide design and construction management services. As of the proposed boundaries, this school will relieve Cahoon, Forest Hills, and Pizzo Elementary Schools.
This change order provides a credit for the direct purchase of materials by the District, in accordance with the Direct Purchase Program.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
FINANCIAL IMPACT (Budgeted: Yes)
EVALUATION
SUBMITTED BY: Jill Edwards, Project Coordinator
Rory Salimbene
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
A 6.10 | |
Hillsborough County Public Schools (Florida) * Mtg.#20080819_298 * Section A Item# 6.10 |