Approve Change Order No. 3 in the Amount of $16,849.82 Extra and Change Order No. 4 in the Credit Amount of $27,762.27 for Classrooms for Kids Addition at
Buckhorn Elementary School

EXECUTIVE SUMMARY

On November 9, 2006, the Board appointed Woodroffe Corporation Architects and Vogel Bros. Building Co. to provide design and construction management services. The scope of work provides for an additional 10 classrooms. This addition is necessary to meet class size reduction requirements.

Change Order No. 3 provides for final reconciliation of the Direct Purchase Program. Change Order No. 4 provides a credit for project savings and the return of unused contingency funds.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

Provide adequate school facilities for the accomplishment of all District Goals and Critical Success Factors.

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Classrooms for Kids.

Contract Status:
Guaranteed Maximum Price: $1,577,793.00
Change Orders Previously Approved: $438,660.05 Credit
Change Order No. 3 Recommended Herein: $16,849.82 Extra
Change Order No. 4 Recommended Herein: $27,762.27 Credit
Revised Guaranteed Maximum Price: $1,128,220.50
Revised Construction Cost: $1,525,200.74

Contract Completion Date: August 4, 2008

EVALUATION

SUBMITTED BY: Ellis Curry, Project Coordinator

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
A 6.18
Hillsborough County Public Schools (Florida) * Mtg.#20081007_301 * Section A Item# 6.18