On February 19, 2008, the Board appointed Rowe Architects, Inc. and Batson-Cook Company to provide design and construction management services. The renovation of existing facilities provides for locker refinishing; interior painting; door hardware, toilet accessories, and other miscellaneous handicap accessibility upgrades; roof refurbishment; replacement of acoustical ceilings; replacement of worn carpet with vinyl composition tile (VCT); and heating, ventilating, and air conditioning (HVAC) and fire sprinkler system replacements. Project completion is scheduled for July 2010.
Approval of the design development phase will allow the architect to proceed with construction documents.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
FINANCIAL IMPACT (Budgeted: Yes)
The project is currently funded at $9,324,688. The estimate of probable cost is $9,322,093. This item is included in the District Capital Outlay: 2 Mill.
EVALUATION
SUBMITTED BY: Eugene Runnels, Project Coordinator
Rory Salimbene
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
A 6.08 | |
Hillsborough County Public Schools (Florida) * Mtg.#20081007_301 * Section A Item# 6.08 |