SUBJECT / RECOMMENDATIONS

Approve Change Order No. 1 in the Net Credit Amount of $92,251.24, Approve 170 Calendar Day Time Extension, and Acceptance of Project for 2007 Water, Wastewater, and Drainage Improvement Projects at
Various Schools

EXECUTIVE SUMMARY

This project was planned by the engineering firm of Key Engineering Associates. On August 21, 2007, the Board awarded the contract to the single qualified bidder, U.S. Water Services.

This change order provides for a reduction of scope at Trapnell Elementary School; additional welded steel plates required due to unforeseen conditions at Dover Elementary School; and 170 calendar day time extension to accommodate a District-requested delay for work at Knights Elementary School.

The engineer advises that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

All Strategic Objectives

FINANCIAL IMPACT (Budgeted: Yes)

This item was included in the District Capital Outlay: Local Millage.

Contract Status:
Contract Sum: $681,900.00
Change Order Recommended Herein: $102,994.15 Credit and $10,742.91 Extra
Revised Contract Sum: $589,648.76
Payments to Date: $342,190.00
Balance Due: $247,458.76
Original Completion Date: March 15, 2008
Time Extension Recommended Herein: 170 Calendar Days
Revised Completion Date: August 31, 2008
Substantial Completion Date: August 31, 2008

EVALUATION

SUBMITTED BY:

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
A 6.24
Hillsborough County Public Schools (Florida) * Mtg.#20081106_303 * Section A Item# 6.24