Hillsborough County Public Schools Facilities
Action Item

DATE: Thursday, November 6, 2008
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

Approve Change Order No. 4 in the Amount of $12,616.07 Extra and Change Order No. 5 in the Credit Amount of $62,885.68 for Classrooms for Kids Addition at
Maniscalco Elementary School

EXECUTIVE SUMMARY

On November 9, 2006, the Board appointed John J. McKenna Architect P.A. and W.G. Mills, Inc. to provide design and construction management services. The scope of work provides for an additional 14 classrooms. This addition is necessary to meet class size reduction requirements.

Change Order No. 4 provides for final reconciliation of the Direct Purchase Program. Change Order No. 5 provides a credit for project savings and the return of unused contingency funds.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

All Strategic Objectives

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Classrooms for Kids.

Contract Status:
Guaranteed Maximum Price: $2,237,545.00
Change Orders Previously Approved: $442,841.00 Credit
Change Order No. 4 Recommended Herein: $12,616.07 Extra
Change Order No. 5 Recommended Herein: $62,885.68 Credit
Revised Guaranteed Maximum Price: $1,744,434.39
Revised Construction Cost: $2,149,558.10

Contract Completion Date: August 4, 2008

EVALUATION

SUBMITTED BY: Eugene Runnels, Project Coordinator

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
A 6.20
Hillsborough County Public Schools (Florida) * Mtg.#20081106_303 * Section A Item# 6.20