Approve Change Order No. 1 in the Amount of $10,124.00 Extra and a Time Extension of 15 Calendar Days for Roof Replacement at
Gaither High School

EXECUTIVE SUMMARY

Harvard Jolly, Inc. was selected from the approved Continuing Services Consultants list to provide design services. The scope of work provides for replacement of a portion of the roof at Gaither High School. On May 20, 2008, the Board awarded the contract for construction to Crowther Roofing & Sheet Metal of Florida, Inc.

This change order provides for cleaning of roof drains required due to unforeseen conditions, and District-requested repairs to a portion of the roof not included in the original replacement scope. A time extension of 15 calendar days is included to adjust for rain delays.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

All Strategic Objectives

FINANCIAL IMPACT (Budgeted: Yes)

This project is included in the District Capital Outlay: Local Millage.

Contract Status:
Guaranteed Maximum Price: $464,329.00
Change Order Recommended Herein: $10,124.00 Extra
Revised Guaranteed Maximum Price: $474,453.00
Revised Construction Cost: $474,453.00

Original Completion Date: August 4, 2008
Time Extension Recommended Herein: 15 Days
Revised Contract Completion Date: August 19, 2008

EVALUATION

SUBMITTED BY: Jill Edwards, Project Coordinator

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004