Facilities Action Item |
DATE: Tuesday, November 18, 2008
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
EXECUTIVE SUMMARY
On March 8, 2005, the Board appointed Ruyle Hayes + Jennewein Architects P.A. and Construct Two Group, Inc. to provide design and construction management services for the addition of a gymnasium at Sligh Middle School.
This change order provides for final reconciliation of the Direct Purchase Program.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
FINANCIAL IMPACT (Budgeted: Yes)
This item is included in the District Capital Outlay: Certificates of Participation Series 2001B.
Contract Status:
Guaranteed Maximum Price: $1,941,041.00
Change Orders Previously Approved: $580,868.45 Extra
Change Order Recommended Herein: $1,364.93 Extra
Revised Guaranteed Maximum Price: $2,523,274.38
Revised Construction Cost: $2,999,263.65
Original Completion Date: December 24, 2006
Time Extension Previously Approved: 129 Calendar Days
Revised Completion Date: May 2, 2007
EVALUATION
SUBMITTED BY: James Lipsey, Project Coordinator
Rory Salimbene
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
A 6.09 | |
Hillsborough County Public Schools (Florida) * Mtg.#20081118_305 * Section A Item# 6.09 |