Facilities
Action Item
|
DATE: Tuesday, December 9, 2008
TO: School Board Members
FROM: MaryEllen Elia, Superintendent
SUBJECT / RECOMMENDATIONS
Approve Change Order No. 2 in the Amount of $119,720.00 Extra for Classrooms for Kids Addition at
Alafia Elementary School
EXECUTIVE SUMMARY
On November 9, 2006, the Board appointed Harvard Jolly, Inc. and The A.D. Morgan Corporation to provide design and construction management services. The scope of work provides for an additional 10 classrooms. This addition is necessary to meet class size reduction requirements.
This change order adds an urgent roof replacement for a portion of the existing facility to the project scope.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
All Strategic Objectives
FINANCIAL IMPACT (Budgeted: Yes)
This item is included in the District Capital Outlay: Classrooms for Kids.
Contract Status:
Guaranteed Maximum Price: $1,738,643.00
Change Order Previously Approved: $360,793.62 Credit
Change Order Recommended Herein: $119,720.00 Extra
Revised Guaranteed Maximum Price: $1,497,569.38
Revised Construction Price: $1,836,999.28
Contract Completion Date: August 4, 2008
EVALUATION
SUBMITTED BY:
Jill Edwards, Project Coordinator
Rory Salimbene
General Manager of Construction
(813) 272-4112
|
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
|
A 6.09
|
Hillsborough County Public Schools (Florida) * Mtg.#20081209_314 * Section A Item# 6.09
|