Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, December 9, 2008
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

Approve Change Order No. 2 in the Amount of $30,746.98 Extra for Renovation at
West Shore Elementary School

EXECUTIVE SUMMARY

On February 13, 2007, the Board appointed Rowe Architects, Inc. and J.B.D. Construction, Inc. to provide design and construction management services. The renovation of existing facilities includes roof and plaster wall repairs; exterior brick repointing, restoration, and sealing; interior painting; upgrades to emergency lighting, telephone, voice/data, closed circuit television (CCTV), and security systems; replacement of the fire alarm system and instructional aids; removal of carpet and refinishing of existing hardwood floors; handicap accessibility upgrades to door hardware, thresholds, and building entries; and the addition of a fire sprinkler system and new parent drop-off.

This change order provides additional materials and labor for the wood floor refinishing, required due to unforeseen conditions.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

All Strategic Objectives

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Local Millage.

Contract Status:
Guaranteed Maximum Price: $2,151,930.00
Change Order Previously Approved: $47,387.00 Extra
Change Order Recommended Herein: $30,746.98 Extra
Revised Guaranteed Maximum Price: $2,230,063.98
Revised Construction Cost: $2,230,063.98

Contract Completion Date: December 15, 2008

EVALUATION

SUBMITTED BY: Alice Sutton, Project Coordinator

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
A 6.19
Hillsborough County Public Schools (Florida) * Mtg.#20081209_314 * Section A Item# 6.19