Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, December 9, 2008
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

Approve Acceptance of Project for HVAC Control System Replacement at
Knights Elementary School and Monroe Middle School

EXECUTIVE SUMMARY

Consulting Engineering Associates, Inc. was selected from the approved Continuing Services Consultants list to provide design services. On May 20, 2008 the Board awarded the contract for construction to the sole bidder, Automated Building Control System, Inc. The scope of work provided for replacement of the heating, ventilating, and air conditioning (HVAC) controls at Knights Elementary School and Monroe Middle School.

The engineer advises that the project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

All Strategic Objectives

FINANCIAL IMPACT (Budgeted: Yes)

These items were included in the District Capital Outlay: Public Education Capital Outlay (PECO) Maintenance.

Contract Status:
Contract Sum: $226,000.00
Payments to Date: $203,400.00
Balance Due: $22,600.00
Revised Construction Cost: $226,000.00

Contract Completion Date: August 18, 2008
Substantial Completion Date: August 8, 2008

EVALUATION

SUBMITTED BY: Ernie MacFerran, Mechanical Engineer

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
A 6.29
Hillsborough County Public Schools (Florida) * Mtg.#20081209_314 * Section A Item# 6.29