Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, January 27, 2009
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

Approve Change Order No. 1 in the Amount of $49,648.97 Extra, including a 10 Calendar Day Time Extension, Approve Change Order No. 2 in the Amount of $33,465.31 Credit, and Acceptance of Project for Minor Renovations at
Egypt Lake Elementary School

EXECUTIVE SUMMARY

This project was planned by the architectural firm of Reliable Group Architects, LLC. On April 15, 2008, the Board awarded the contract to the low bidder, Eveland Brothers, Inc.

Change Order No. 1 provides for modifications to flooring work required due to unforeseen conditions, and the addition of needed window replacements to the project. A ten day time extension is included for completion of the additional work. Change Order No. 2 provides a credit for the direct purchase of materials in accordance with the Direct Purchase Program.

The architect advises that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

All Strategic Objectives

FINANCIAL IMPACT (Budgeted: Yes)

This item was included in the District Capital Outlay: Public Education Capital Outlay (PECO).
Contract Status:
Contract Sum: $262,780.00
Change Order No. 1 Recommended Herein: $49,648.97 Extra
Change Order No. 2 Recommended Herein: $33,465.31 Credit
Revised Contract Sum: $278,963.66
Payments to Date: $204,432.56
Balance Due: $74,531.10
Original Completion Date: August 5, 2008
Time Extension Recommended Herein: 10 Calendar Days
Revised Completion Date: August 15, 2008
Substantial Completion Date: August 15, 2008

EVALUATION

SUBMITTED BY:

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
A 6.33
Hillsborough County Public Schools (Florida) * Mtg.#20090127_342 * Section A Item# 6.33