EXECUTIVE SUMMARY
On November 22, 2005, the Board appointed Holmes Hepner and Associates Architects and Greater Bay Construction Co., Inc. to provide design and construction management services. This facility was a modification of the Pizzo Elementary School design. The school opened in August 2007 and relieved overcrowding at Citrus Park, McKitrick, and Schwarzkopf Elementary Schools.
The architect advises that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
FINANCIAL IMPACT (Budgeted: Yes)
This item was included in the District Capital Outlay: Certificates of Participation Series 2002.
Contract Status:
Guaranteed Maximum Price: $11,927,498.00
Change Orders Previously Approved: $3,169,710.21 Credit
Revised Guaranteed Maximum Price: $8,757,787.79
Payments to Date: $8,674,348.83
Balance Due: $83,438.96
Revised Construction Cost: $11,860,592.94
Contract Completion Date: June 25, 2007
Substantial Completion Date: August 10, 2007
EVALUATION
SUBMITTED BY: Ellis Curry, Project Coordinator
Rory Salimbene
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |
A 6.28 | |
Hillsborough County Public Schools (Florida) * Mtg.#20090127_342 * Section A Item# 6.28 |