Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, January 27, 2009
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

Approve Change Order No. 4 for a Time Extension of 12 Calendar Days for Classrooms for Kids Addition at
Newsome High School

EXECUTIVE SUMMARY

On November 9, 2006, the Board appointed Wilder Architecture, Inc. and Peter R. Brown Construction, Inc. to provide design and construction management services. The scope of work provides for 24 additional classrooms. This addition is necessary to meet class size reduction requirements.

This change order provides for fire alarm system modifications required by the Building Code Manager. Included is a time extension of 12 calendar days for completion of the work.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

All Strategic Objectives

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Classrooms for Kids.

Contract Status:
Guaranteed Maximum Price: $3,890,754.00
Change Orders Previously Approved: $768,777.10 Credit
Change Order Recommended Herein: $0.00 Extra
Revised Guaranteed Maximum Price: $3,121,976.90
Revised Construction Cost: $3,732,918.77

Original Completion Date: July 11, 2008
Time Extension Recommended Herein: 12 Calendar Days
Revised Completion Date: July 23, 2008

EVALUATION

SUBMITTED BY: Alice Sutton, Project Coordinator

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
A 6.20
Hillsborough County Public Schools (Florida) * Mtg.#20090127_342 * Section A Item# 6.20