Approve Construction Documents and Guaranteed Maximum Price for Life Skills Learning Center at
Gary Adult High School

EXECUTIVE SUMMARY

On May 20, 2008, the Board appointed Long & Associates Architects/Engineers, Inc. and Halfacre Construction Company to provide design and construction management services for relocatable and modular facilities. The scope of work at Gary Adult High School provides for installation of a modular facility to serve as a Life Skills Learning Center.

Approval of the guaranteed maximum price will establish a cost for the project.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

All Strategic Objectives

FINANCIAL IMPACT (Budgeted: Yes)

Construction cost is warranted at $55,373.79. The construction budget is $55,374. Funding will be derived from Individuals with Disabilities Education Act.

EVALUATION

SUBMITTED BY: Ken Tomberlin, Relocatable Facilities Manager

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
A 6.03d
Hillsborough County Public Schools (Florida) * Mtg.#20090210_343 * Section A Item# 6.03d