Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, February 10, 2009
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

Approve Change Order No. 5 in the Amount of $32,458.61 Extra, Change Order No. 6 in the Credit Amount of $464,503.30, and Acceptance of Project for Classroom and Field House Addition and Remodel at
Armwood High School

EXECUTIVE SUMMARY

On November 9, 2006, the Board appointed Ranon & Partners, Inc. Architects and Ellis Construction Company, Inc. to provide design and construction management services. The scope of work included the addition of 16 classrooms required for class size reduction. The field house addition included boys and girls locker rooms, showers and toilets, office and planning area. The field house was funded by private donations and matching funds from the District.

Change Order No. 5 provides for final reconciliation of the Direct Purchase Program. Change Order No. 6 provides a credit for project savings and the return of unused contingency funds.

The architect advises that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

All Strategic Objectives

FINANCIAL IMPACT (Budgeted: Yes)

This item was included in the District Capital Outlay: Classrooms for Kids 2006 ($2,463,713), Community Investment Tax ($1,482,263), Community Sources (Private donations $550,000), and Local Millage (Matching funds $50,000).
Contract Status:
Guaranteed Maximum Price: $4,595,976.00
Change Orders Previously Approved: $1,126,286.77 Credit
Change Order No. 5 Recommended Herein: $32,458.61 Extra
Change Order No. 6 Recommended Herein: $464,503.30 Credit
Revised Guaranteed Maximum Price: $3,037,644.54
Payments to Date: $3,027,603.12
Balance Due: $10,041.42
Revised Construction Cost: $4,151,640.96
Contract Completion Date: July 21, 2008
Substantial Completion Date: July 15, 2008

EVALUATION

SUBMITTED BY: Alice Sutton, Project Coordinator

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
A 6.09
Hillsborough County Public Schools (Florida) * Mtg.#20090210_343 * Section A Item# 6.09