Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, March 10, 2009
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

Approve Change Order No. 4 in the Credit Amount of $4,460.40 for Classrooms for Kids Addition at
Valrico Elementary School

EXECUTIVE SUMMARY

On November 9, 2006, the Board appointed Carruthers & Associates Architects P.A. and Manhattan Construction Company to provide design and construction management services. The scope of work provides for an additional 16 classrooms. This addition is necessary to meet class size reduction requirements.

This change order provides for final reconciliation of the Direct Purchase Program.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

All Strategic Objectives

FINANCIAL IMPACT (Budgeted: Yes)

This item is included in the District Capital Outlay: Classrooms for Kids.

Contract Status:
Guaranteed Maximum Price: $2,812,695.00
Change Orders Previously Approved: $408,665.97 Credit
Change Order Recommended Herein: $4,460.40 Credit
Revised Guaranteed Maximum Price: $2,399,568.63
Revised Construction Cost: $2,871,740.68

Contract Completion Date: August 4, 2008

EVALUATION

SUBMITTED BY: Eugene Runnels, Project Coordinator

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
A 6.14
Hillsborough County Public Schools (Florida) * Mtg.#20090310_345 * Section A Item# 6.14