Hillsborough County Public Schools Facilities
Action Item

DATE: Tuesday, May 19, 2009
TO: School Board Members
FROM: MaryEllen Elia, Superintendent

SUBJECT / RECOMMENDATIONS

Approve Time Extension of 117 Calendar Days, and Acceptance of Project for Softball Field Lighting at
Armwood High School

EXECUTIVE SUMMARY

Anston-Greenlees, Inc. was selected from the approved Continuing Services Consultants list to provide design services. On April 24, 2007, the Board awarded the contract to M. Gay Constructors, Inc., the low bidder. The scope of work provided for demolition of existing lighting and installation of field lights for the softball field at Armwood High School.

Change Order No. 1 provides for a time extension of 117 calendar days, required by the District to avoid impacts to the concurrent construction of a classroom addition.

The engineer advises that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

All Strategic Objectives

FINANCIAL IMPACT (Budgeted: Yes)

This item was included in the District Capital Outlay: 2 Mill

Contract Status:
Contract Sum: $90,900.00
Change Order No. 1 Recommended Herein: 117 Calendar Day Time Extension
Payments to Date: $90,900.00
Balance Due: $-0-
Contract Completion Date: August 16, 2007
Revised Completion Date: December 11, 2007
Substantial Completion Date: December 11, 2007

EVALUATION

SUBMITTED BY:

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
A 6.10
Hillsborough County Public Schools (Florida) * Mtg.#20090519_351 * Section A Item# 6.10