Approve Acceptance of Project for Renovation at
Knights Elementary School

EXECUTIVE SUMMARY

On July 11, 2006, the Board appointed Reynolds, Smith & Hills, Inc. and Mathews Construction to provide design and construction management services. The renovation of existing facilities provided for a new walkway canopy and fire sprinkler system; reconfiguration of driveways and visitor parking; interior and exterior painting; and replacement of roof, plumbing fixtures, exterior doors, low voltage systems, and heating, ventilating, and air conditioning (HVAC) equipment.

The architect advises that the referenced project is finally complete in accordance with the plans and specifications and other contract documents and recommends Board acceptance.

ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)

All Strategic Objectives

FINANCIAL IMPACT (Budgeted: Yes)

This item was included in the District Capital Outlay: Capital Outlay and Debt Service (CO and DS) 06A ($3,000,000) and Community Investment Tax (CIT) 06 ($450,000).

Contract Status:
Guaranteed Maximum Price: $3,450,000.00
Change Orders Previously Approved: $994,375.11 Credit
Revised Guaranteed Maximum Price: $2,455,624.89
Payments to Date: $2,449,673.92
Balance Due: $5,950.97
Revised Construction Cost: $2,987,819.28

Original Completion Date: July 14, 2008
Time Extension Previously Approved: 1 Calendar Day
Revised Completion Date: July 15, 2008
Substantial Completion Date: July 18, 2008

EVALUATION

SUBMITTED BY: Jill Edwards, Project Coordinator

Rory Salimbene
General Manager of Construction
(813) 272-4112
Cathy L. Valdes
Chief Facilities Officer
(813) 272-4004
A 6.13a
Hillsborough County Public Schools (Florida) * Mtg.#20090421_348 * Section A Item# 6.13a