On May 20, 2008, the Board appointed Halfacre Construction Company to provide construction management services for installation, relocation, and removal of relocatable facilities (portables). The scope of work at Woodbridge Elementary School provides for disconnection and removal of 37 portable classrooms installed to support renovation of the school. The scope also includes removal of all temporary concrete walkways and restoration of the portable site.
Approval of the guaranteed maximum price will establish the cost for the project.
ANNUAL DISTRICT GOAL(S) AND CRITICAL SUCCESS FACTOR(S)
FINANCIAL IMPACT (Budgeted: Yes)
Construction cost is warranted at $162,134. The construction budget is $162,134. This item is included in the District Capital Outlay: Local Millage.
EVALUATION
SUBMITTED BY: Ken Tomberlin, Relocatable Facilities Manager
Rory Salimbene
General Manager of Construction (813) 272-4112 |
Cathy L. Valdes
Chief Facilities Officer (813) 272-4004 |